TODAY’S STUDY: HOW GOOGLE’S WIRES FOR OFFSHORE WIND WILL MAKE A DIFFERENCE
Question: What do the founders of Google and Ty Cobb, baseball's Georgia Peach and one of its all-time-greats, have in common?
Google just announced a second big wind buy in California’s Tehachapi wind energy bonanza, bringing its investment in New Energy to over three-fourths of a BILLION dollars. Its bets:
[1] $280 million in SolarCity, a rooftop solar financing and installation company,
[2] $100 million in Oregon’s 845 megawatt Shepherd’s Flat project, the world’s largest wind farm,
[3] $38.8 million in 169.5 megawatts of North Dakota wind,
[4] a power purchase agreement (PPA) giving subsidiary Google Energy access to 114 megawatts from an Iowa wind farm,
[5] a PPA giving Google Energy access to 100 megawatts from a wind farm now under construction in Oklahoma,
[6] $168 million in a BrightSource Energy solar power plant now under construction in California’s Mojave Desert,
[7] $5 million in a solar photovoltaic (PV) power plant in Germany, near Berlin,
most significantly
[8] one third of the $6 billion Atlantic Wind Connection (AWC), a transmission backbone system for offshore wind along the eastern seaboard,
and
[9] 9 or more ventures in startups, including ActaCell (batteries), Aptera (electric vehicles), Next Autoworks (advanced efficiency carmaker), Alta Rock (geothermal producer), RelayRides (car sharing), WeatherBill (weather insurance), Silver Spring Networks (smart grid technologies), Cool Planet Biofuels (next generation biofuels), Transphorm (power conversion).
It is an impressive portfolio and most impressive of all is that the biggest single bet is on the long term future of offshore wind on the East Coast. Offshore wind is one of the New Energy sources most disdained by the Old Energy establishment.
Google's bet is not on wind itself but on the wires that will deliver the wind from offshore projects to the onshore distribution system. It assumes the success of offshore wind technology.
It is a familiar role for Google, one that made the company what it is today. Larry (Page) and Sergey (Brin) took internet technology and the human pursuit of knowledge as givens and created the best way ever known to connect the two.
In the same way, they see that offshore wind technology and the human need for electricity are givens. The Atlantic Wind Connection (AWC) is simply the best way to connect them. As the report highlighted below describes, AWC has every chance of playing just as vital a role as the search engine did and being at least as lucrative.
Since the report was written, the Federal Energy Regulatory Commission ratified Google’s faith in the project by legitimizing a fixed profit (12.59%). This has allowed AWC to move ahead in the regulatory process. The ambitious transmission scheme still has a lot of red tape to work through. It will likely not be in service before the middle of this decade. But that will be just about when offshore wind builders need it.
The other key to Google’s success was that just when internet users were looking for the right search engine, there it was. AWC looks positioned to have the same perfect timing.
Ty Cobb, one of baseball’s first Hall-Of-Famers and one of the founding investors in a little company called Coca-Cola, said that by carefully watching the game a player could find ways to make his own “breaks.” Similarly, it looks like Larry and Sergey, seeing that the wind resource along the Atlantic coast is unsurpassed and the need in the cities there for electricity will only grow, are taking a page from the Georgia Peach's playbook and planning to get “lucky” again.
They are betting on the undeniable logic of New Energy.
An Assessment of the Public Policy, Reliability, Congestion Relief, and Economic Benefits of the Atlantic Wind Connection Project
Johannes Pfeifenberger and Samuel Newell, December 2010 (The Brattle Group)
Executive Summary
The AWC Companies have asked The Brattle Group to analyze and quantify some of the public policy, reliability, congestion relief, and other economic benefits associated with the Atlantic Wind Connection Project (“AWC Project” or “Project”).
The AWC Project is a high-voltage direct-current (“HVDC”) offshore transmission backbone spanning approximately 250 miles from northern New Jersey to southern Virginia. It can integrate 6,000 MW of offshore wind generation into PJM’s onshore grid with significant benefits over the radial interconnection of individual wind farms. The AWC Project, which will be built in five phases, can also be used to transmit up to 2,000 MW of energy and capacity between interconnection points along the coast, providing an offshore reinforcement to the existing onshore grid in the congested Mid-Atlantic power market.
The offshore wind generation interconnected through the AWC Project will reduce system wide production costs from fossil-fuel fired generation by $1.1 billion per year with a 20-year present value of $12 billion. It will also reduce customer locational marginal prices (“LMPs”) by approximately $1.6 billion per year (net of offsetting impacts on capacity market prices), with a present value of $17 billion. In addition, the development of the AWC Project and associated offshore wind generation will reduce CO2 emissions by 16 million tons annually, the equivalent of taking 3 million cars off the road. Depending on the degree of in-region manufacturing and supply of equipment and logistical support, these wind and transmission investments will support between 130,000 and 260,000 full-time-equivalent years of employment and provide significant associated economic stimulus benefits for the local economy.
click to enlarge
The AWC Project will enable these wind-related benefits more quickly and with major economic advantages over relying on wind developers to interconnect their own wind farms via radial AC lines. Through its scale and HVDC technology, the AWC Project provides the following comparative benefits:
¨ It enables states to meet their renewable energy policy requirements and goals through streamlined permitting, greater scale, and lower costs;
¨ It maintains and improves the reliability and operation of the transmission grid; and
¨ It provides congestion relief and other economic benefits in the congested Mid-Atlantic power market
Compared to the radial interconnection of individual wind plants, the AWC Project offers total benefits of $9-$15 billion, including the avoided costs of radial transmission lines. These total benefits far exceed the approximately $5 billion cost of constructing the Project.
click to enlarge
STATE RPS REQUIREMENTS AND ECONOMIC BENEFITS OF OFFSHORE RENEWABLE POWER DEVELOPMENT
The AWC Project provides a platform on which offshore wind developers can interconnect their wind farms with significantly reduced siting, permitting, and interconnection barriers. This will help meet state renewable energy requirements and other state and federal energy, environmental, and economic policy goals. Offshore wind generation facilitated by the AWC Project will lower CO2 emissions by reducing coal, gas, and oil usage, and it will reduce energy prices across the PJM footprint. The Project will also enhance reliability and reduce congestion in what the Department of Energy (“DOE”) has designated as one of the most congested National Interest Electric Transmission Corridors. Importantly, this is true of the AWC Project whether viewed without wind build out, full wind build-out, or simply in comparison to a scenario in which offshore wind is interconnected by radial transmission lines.
The Mid-Atlantic region offers the most abundant and most attractive offshore wind resources in the country. The AWC Project can help the Mid-Atlantic and other PJM states take advantage of this resource to achieve their RPS requirements. In doing so, the Project offers significant economic benefits compared to radial interconnections of individual offshore wind farms. By reducing siting, permitting, and interconnection barriers to wind development, the Project will expedite the installation of offshore wind on a scale that very likely spurs the development of local industry to provide equipment and services, which will substantially lower the cost of offshore wind development.
click to enlarge
Of particular importance, the AWC Project’s HVDC backbone and AC-DC converters are controllable which, unlike the typical radial transmission interconnections, allows for optimal power transfers and injections of offshore generation in real time. This enhances reliability and relieves transmission congestion, which lowers system-wide electricity production costs. Compared to radially interconnecting individual offshore wind plants, the AWC Project is a more effective solution for developing Mid-Atlantic offshore wind resources. It provides significantly higher economic, reliability, congestion relief, operating, and environmental benefits to the PJM grid and to the region.
The AWC Project helps meet states’ RPS policies, which require load serving entities to buy increasing amounts of energy from renewable resources, including offshore wind. PJM projects that meeting these state RPS requirements in its footprint would require up to 25,000 MW of wind by 2015 and 50,000 MW by 2025. Of the states directly interconnected by the AWC Project, New Jersey requires 22.5% renewables by 2020, Delaware 25% by 2025, Maryland 20% by 2022, and Virginia has a goal of 15% by 2025.
Offshore wind power has received an increasing amount of public policy attention as a key resource for the eastern U.S. because it is abundant and located close to load centers. In contrast, other local renewable resources are scarce and remote resources (such as onshore wind in the Midwest) would require major transmission investments without much local economic development benefit to the states.
click to enlarge
The AWC Project could deliver 6,000 MW of offshore wind energy, closing approximately 75% of the gap toward the 8,000 MW of new offshore wind that would be sufficient to meet the 2020 RPS requirements of New Jersey, Delaware, Maryland and Virginia, and providing nearly 65% of the requirement by 2025—before considering the potential demand for offshore wind from other states. Moreover, since wind conditions rarely allow entire wind farms to simultaneously generate at their maximum rated capacity, it is more cost effective to install wind capacity in excess of the transmission capacity to maximize the value of the overall investment. In our analysis of benefits, we have assumed that 6,600 MW of nameplate wind generation would be interconnected to the AWC Project, which will result in 10% additional wind energy generated with only 0.2% in curtailments.
Developing this amount of offshore wind generation will require an overall investment of approximately $30 billion. This investment has to be considered in the context of associated benefits. As shown in Table 1, integration of the 6,600 MW of offshore wind generation facilitated by the AWC Project will reduce customer locational marginal prices (“LMPs”) by approximately $1.6 billion per year (net of offsetting impacts on capacity market prices). Our analysis using the PROMOD simulation model shows that this benefit is widespread: load weighted annual average LMPs decrease by approximately $6/MWh in New Jersey, by $2-4/MWh in Delaware, Maryland and Virginia, by $2-5/MWh in Pennsylvania, and by $0.5-1.6/MWh in western PJM.
In addition, the development of offshore wind will create jobs and economic stimulus for the local economy, as shown in Table 2 above. As Table 2 shows, the overall magnitude of the economic stimulus benefits of the offshore wind investments to the local economies is significant. However, the magnitude of this economic benefit also strongly depends on the extent to which wind turbines and other plant and equipment are manufactured within the Mid-Atlantic region (rather than being imported) and the extent to which construction services and logistical support are provided by companies and employees within the region. Achieving a high in-region provision of these equipment and services will require a scale of offshore wind power development that justifies the investment in manufacturing and logistical facilities. The AWC Project facilitates achieving the necessary scale, as discussed below.
click to enlarge
There are also other benefits and costs, including the capacity value of wind, wind integration costs, and the AWC Project-specific benefits discussed below.
While we recognize the above benefits and costs of offshore wind generation, the focus of our analysis was to identify the public policy, reliability, congestion relief, and other economic benefits of the AWC Project itself. We do so primarily by comparing the Project to more conventional ways to interconnect offshore wind through radial transmission lines.
AWC PROJECT COSTS
We compared both the costs and benefits of the AWC Project versus radial alternatives. The AWC Project is able to reliably deliver 6,000 MW of offshore wind power and additionally provide a fully controllable 2,000 MW HVDC transmission path between southern Virginia and northern New Jersey at a total construction cost of approximately $5 billion. In comparison, we estimate that delivering 6,000 MW of wind power with radial transmission lines from individual wind plants to shore would incur construction costs of $3.4 billion to $5.3 billion without offering the substantial additional public policy, reliability, congestion relief, and other economic benefits we have identified and partially quantified for the AWC Project.
click to enlarge
PUBLIC POLICY BENEFITS ASSOCIATED WITH THE AWC PROJECT
The AWC Project will support meeting the states’ renewable energy goals by reducing permitting and planning barriers and achieving significant economies of scale for offshore wind development. The Project creates a one-stop process for landing-point selection, state environmental siting, and PJM transmission planning. Compared to a plant-by-plant permitting and transmission planning process, this will reduce development barriers and provide a platform that increases the certainty, ramp-up, and scale of offshore wind development in the Mid-Atlantic region. In addition, the AWC Project requires fewer landing points, has a smaller environmental footprint, and allows the development of offshore wind locations independently of these landing points.
Increased scale and predictability of offshore wind development facilitated by the AWC Project offers the prospect of significant cost savings for almost every aspect of offshore wind development. It will facilitate investments in local manufacturing of wind turbines and related components and the development of more cost-effective construction and logistical infrastructure. We estimate that streamlined permitting and increased scale that allows local manufacturing and sourcing will reduce total offshore costs by approximately 20 percent. Based on $30 billion of offshore wind generation investment supported by the AWC Project, this results in total cost reductions of approximately $6.0 billion. In addition, promoting in-region manufacturing and sourcing results in significantly greater employment and economic development benefits, as indicated by the difference between “low” and “high” in-region manufacturing benefits…
click to enlarge
RELIABILITY AND OPERATIONAL BENEFITS OF THE AWC PROJECT
The AWC Project will provide significant reliability and operational benefits. The AWC Project will likely reduce the long-term need for costly enhancements to the existing onshore transmission system. This is because: (a) the Project can be designed to interconnect at the strongest onshore nodes, which is less likely to be achieved by interconnecting individual wind farms; (b) the Project’s 2,000 MW transfer capability between landing points in Virginia, Maryland, Delaware, and New Jersey reinforces the onshore grid in the constrained Mid-Atlantic region, reducing the need for future onshore reinforcements; and (c) the Project’s controllable HVDC technology provides PJM with additional flexibility to address reliability challenges whenever they arise.
The capabilities of the Project’s advanced HVDC technology also provide operating benefits that enhance reliability and reduce the cost of system operations. These include: (a) the ability to redirect power flows instantaneously to address system contingencies; (b) improved system stability; (c) voltage support and improved reactive performance; and (d) black start capability. The Project further provides for more reliable delivery of offshore wind power than individual radial connections by being able to redirect power away from landing points with temporary reliability-related transmission constraints.
We have not quantified the economic value of these reliability and operational benefits, nor have we quantified the value of the Project’s specific reliability benefits. However, if the AWC Project avoids the need for even one major onshore transmission project, the savings would likely exceed $1 billion.
click to enlarge
CONGESTION RELIEF AND OTHER ECONOMIC BENEFITS OF THE AWC PROJECT RELATIVE TO A RADIAL ALTERNATIVE
The Project’s offshore backbone and controllability allows energy from offshore wind plants or onshore interconnection points to be transmitted to the interconnection points with the highest LMPs, thereby reducing congestion and overall costs compared to a radial system that simply delivers power from individual offshore wind plants irrespective of onshore grid congestion. We analyzed the economic value of this congestion relief using Ventyx’s PROMOD simulation model. Working with Ventyx staff, we simulated market conditions for 2016 with the addition of 6,600 MW of nameplate offshore wind generation interconnected in two ways: one case with the AWC Project and an alternative case with radial interconnections. These simulations showed that the AWC Project significantly reduces system-wide congestion costs by $196 million annually compared to radial interconnections of individual wind plants. Most of the relief occurs on constraints near the wind power injection points and also on constraints from western Pennsylvania into eastern PJM. Compared to the radial interconnection of individual wind plants, the congestion relief provided by the AWC Project helps to reduce production costs by $33 million per year or by approximately $350 million over the initial 20 years of the Project.
The LMP benefits from the AWC Project with full wind build-out (compared to a Base Case without AWC Project and without offshore wind) were described above. On average, these benefits are greater than with radially interconnecting the same amount of wind. The AWC Project will reduce LMPs, especially in the “EMAAC” region of PJM, compared to the radial alternative. These price impacts would save PJM customers approximately $126 million per year or $1.35 billion over 20 years. However, the lower LMPs relative to radial interconnections will increase capacity prices, which offsets $110 million annually ($1.2 billion over 20 years) of the AWC Project’s incremental LMP benefit…
click to enlarge
The above estimates significantly understate the value that the AWC Project will provide under real-time system operations. This is because a number of operational factors that cause price volatility in the real-time market are not captured in PROMOD simulations, including wind generation uncertainty and forecasting errors, load forecasting errors, sudden outages of generation units, transmission outages, unexpected loop flows from neighboring regions, and ramp-rate limitations on generators. Analysis of historical hourly day-ahead and real-time LMP differentials among the AWC Project’s interconnection points shows that the ability to control power flows in real time is worth approximately twice as much as in the day-ahead market. Since PROMOD simulations are more comparable to the day-ahead market than the real-time market, we estimate that the Project’s real-time congestion-relief value will add at least $310 million to the simulation-based production cost savings over the initial 20 years of the Project.
The AWC Project would also provide capacity value that radial interconnections would not. In addition to transmitting the capacity value of 6,000 MW of offshore wind—which PJM is likely to count less than 2,000 MW for resource adequacy purposes—the AWC Project will be able to transmit 2,000 MW of capacity from unconstrained southern Virginia northward into the constrained EMAAC region of PJM. The Project also allows transmission of capacity between any constrained subareas within EMAAC if capacity prices were to differ across these subareas again in the future. We have not forecasted future capacity market conditions and the precise impact of the Project on such future prices. However, using a scenario analysis PJM recently conducted to assess the impact of added transfer capability on 2013/14 capacity prices, and assuming that these price impacts would be realized for only five years over the entire life of the Project, we estimate that the AWC Project would reduce retail customers’ capacity payments by approximately $2.1 billion in EMAAC and by approximately $2.7 billion in all of PJM. Even without considering the capacity price benefits to all retail customers, the value of transmitting up to 2,000 MW of capacity from southern Virginia to EMAAC for five years would be worth $180 million.
Finally, the AWC Project will also decrease emissions. By facilitating the development of offshore wind more quickly and at greater scale than if individual wind developers had to plan, permit, and build their own interconnections, the 6,600 MW of offshore wind interconnected via the AWC Project would eliminate 16 million tons of CO2 emissions from fossil-fuel-fired generation per year…
click to enlarge
SUMMARY
Table 3 summarizes the benefits discussed and quantified in our comparison of the AWC Project to radially interconnected individual wind farms. As Table 3 shows, the pproximately $5 billion construction cost of the AWC Project is more than offset by a number of economic benefits that the Project offers over a plant-by-plant development of offshore wind generation and the interconnection of individual wind power plants through radial HVAC transmission links to the onshore grid. Interconnecting offshore wind with the AWC Project provides $9-15 billion of benefits over a radial approach (including the avoided costs of radial transmission lines), without considering the economic value of reliability and operating benefits we did not quantify.