NewEnergyNews: ORIGINAL REPORTING: GRID OF THE FUTURE: HOW TRANSMISSION AND NEW TECHNOLOGIES CAN WORK TOGETHER/

NewEnergyNews

Gleanings from the web and the world, condensed for convenience, illustrated for enlightenment, arranged for impact...

The challenge now: To make every day Earth Day.

YESTERDAY

THINGS-TO-THINK-ABOUT WEDNESDAY, August 23:

  • TTTA Wednesday-ORIGINAL REPORTING: The IRA And The New Energy Boom
  • TTTA Wednesday-ORIGINAL REPORTING: The IRA And the EV Revolution
  • THE DAY BEFORE

  • Weekend Video: Coming Ocean Current Collapse Could Up Climate Crisis
  • Weekend Video: Impacts Of The Atlantic Meridional Overturning Current Collapse
  • Weekend Video: More Facts On The AMOC
  • THE DAY BEFORE THE DAY BEFORE

    WEEKEND VIDEOS, July 15-16:

  • Weekend Video: The Truth About China And The Climate Crisis
  • Weekend Video: Florida Insurance At The Climate Crisis Storm’s Eye
  • Weekend Video: The 9-1-1 On Rooftop Solar
  • THE DAY BEFORE THAT

    WEEKEND VIDEOS, July 8-9:

  • Weekend Video: Bill Nye Science Guy On The Climate Crisis
  • Weekend Video: The Changes Causing The Crisis
  • Weekend Video: A “Massive Global Solar Boom” Now
  • THE LAST DAY UP HERE

    WEEKEND VIDEOS, July 1-2:

  • The Global New Energy Boom Accelerates
  • Ukraine Faces The Climate Crisis While Fighting To Survive
  • Texas Heat And Politics Of Denial
  • --------------------------

    --------------------------

    Founding Editor Herman K. Trabish

    --------------------------

    --------------------------

    WEEKEND VIDEOS, June 17-18

  • Fixing The Power System
  • The Energy Storage Solution
  • New Energy Equity With Community Solar
  • Weekend Video: The Way Wind Can Help Win Wars
  • Weekend Video: New Support For Hydropower
  • Some details about NewEnergyNews and the man behind the curtain: Herman K. Trabish, Agua Dulce, CA., Doctor with my hands, Writer with my head, Student of New Energy and Human Experience with my heart

    email: herman@NewEnergyNews.net

    -------------------

    -------------------

      A tip of the NewEnergyNews cap to Phillip Garcia for crucial assistance in the design implementation of this site. Thanks, Phillip.

    -------------------

    Pay a visit to the HARRY BOYKOFF page at Basketball Reference, sponsored by NewEnergyNews and Oil In Their Blood.

  • ---------------
  • WEEKEND VIDEOS, August 24-26:
  • Happy One-Year Birthday, Inflation Reduction Act
  • The Virtual Power Plant Boom, Part 1
  • The Virtual Power Plant Boom, Part 2

    Monday, December 29, 2014

    ORIGINAL REPORTING: GRID OF THE FUTURE: HOW TRANSMISSION AND NEW TECHNOLOGIES CAN WORK TOGETHER

    Grid of the future: How transmission and new technologies can work together; Ex-FERC Chairman: "We may get to the point where we don't need a network of wires. But I can't foresee that."

    Herman K. Trabish, October 15, 2014 (Utility Dive)

    Far from threatening the grid, non-transmission alternatives can enhance reliability and complement existing and new transmission infrastructure, according to a new study.

    Implementing these resources begins with understanding each option, and it ends with filling the system’s needs with the most economical set of options.

    “The first question planners need to ask is ‘What do I need for the system?’” Julia Frayer, managing director of London Economics International and lead author of Market Resource Alternatives: An Examination of New Technologies in the Electric Transmission Planning Process, told Utility Dive. “Then it is important to study transmission and all the Market Resource Alternatives (MRAs) that can help meet that need.”

    MRAs—London Economics's term for non-transmission alternatives—include energy efficiency, demand response, utility-scale generation, distributed generation, energy storage, and smart grid.

    To keep distortion and prejudice out of the study of MRAs, it is important “to make sure the cost-benefit analysis is comprehensive,” Frayer said.

    Complementarity, not substitution

    "We are talking about what the Federal Energy Regulatory Commission (FERC) meant in Order 1000 when it told transmission system planners they had to consider ‘non-transmission alternatives,’” former FERC Chair Jim Hoecker told Utility Dive, explaining why the transmission trade groupWIRES, which he advises, commissioned the study.

    “MRAs are important but they aren’t all deployed the same way and they have different characteristics,” Hoecker said. “Sometimes they help rationalize the transmission planning process and sometimes they have nothing to do with it.”

    The term NTA [non-transmission alternatives] contains the implication that alternatives will substitute for transmission, Frayer said, hence the change in terminology to Market Resource Alternatives. But they are all part of an integrated electric system: Transmission needs generation and generation needs transmission.

    “And that applies to all the MRAs,” Frayer added. “The system does its job, to deliver electricity, only because all the components are there. Substitution is the worst word to describe that. We need to talk about complementarity.”

    “Each of the technologies has enormous benefits and will be absolutely critical to the future of the electric system,” Hoecker said. “But it is a dangerous misunderstanding to think these technologies simply obviate the need for a robust transmission system. We may get to the point where we don’t need a network of wires. But I can’t foresee that.”

    Moon charts

    The WIRES report uses what Frayer called “moon charts” to show complementarities between transmission and MRAs in providing energy, capacity, ancillary services, system loss reductions, system lifespan, continuous service, and locational services for wholesale and retail customers. The objective, she said, was to understand how MRAs fit into the transmission planning process.

    Transmission combined with the technologies provides the full range of services, the study found,. The MRA technologies, even with transmission, do not. To select between the options, a cost-benefit analysis is vital for planners. But a “least cost analysis” is insufficient. It must be comprehensive.

    “One must consider the ability of a solution, be that MRAs or transmission, to provide benefits and services to various customer classes and over varying geographies and time dimensions," Frayer said.

    “All technologies meet local needs,” she added. “If you are pairing local needs with the need for capacity, utility scale generation and transmission are similar. But for transmission to provide capacity, it needs to be paired with generation.”

    All of the options also have a degree of “operational uncertainty” and “negative and positive externalities” that must be weighed in any cost-benefit analysis.

    Energy efficiency and demand response are similar in providing capacity, Frayer explained, but each is limited in a different way. “Efficiency is expected to provide capacity for many hours whereas DR provides it only for a subset of hours—at peaks or when the system is under stress," she said.

    Not choosing between A and B

    The study concludes with a set of case studies that identify where planning methodologies and modeling techniques succeeded or failed. “Sometimes we predispose our modeling analysis so we only think of substitutes,” Frayer said. “Instead of choosing between A and B, we should be asking what amount of A and what amount of B will provide the best solution.”

    When the Bonneville Power Administration (BPA) was planning for its I-5 Corridor Reinforcement Transmission Project, new lines—as well as energy efficiency, demand response, distributed generation, and re-dispatch of existing generation—were considered to meet a “reliability need.”

    BPA concluded the MRAs alone were “potentially insufficient and too risky to meet the identified reliability needs over the long term.”

    Despite operational uncertainties, BPA invested in energy efficiency and demand response as a complementary and interim measure “along with transmission to increase the net benefit to the system and customers.”

    In another case study, the California Public Utilities Commission approved theTehachapi Renewable Transmission Project (TRTP) to meet public policy goals, the paper reports, but “no economic analysis was performed.”

    If a full cost-benefit analysis that included RPS goals or carbon reductions had been done by the commission or by the California Independent System Operator, it adds, “more transmission investments may have been appropriate… [and] the complementarity between transmission and generation would have spurred additional wind developments in the wind abundant regions, which may have created further benefits to customers.”

    And in Texas, where there is nearly 13,000 MW of installed wind capacity, “transmission was used to promote the development of renewable resources,” the study notes. Putting together the tools and techniques

    “None of this is rocket science and we are not asking planners to change everything they do,” Frayer said. “These tools and techniques are not novel, untested, or experimental. They are all in use by planning departments. We just suggest they put them together in a different order so they are not looking at substitution only.”

    “This is a new vision of how the electric system will work,” Hoecker said. “It says that MRAs, collectively and individually, as important as they are, are rarely a substitute for the investment in transmission we really need right now. If people defer that investment long enough, they are going to have reliability problems and life is going to get a little more expensive.”

    click here for more